The site from orbitStegra steelworks, BodenSteel plant under construction · Sweden


Drag the slider to compare July 2021 with July 2026. Click a number to see what we noticed there.
This view is about 8 km across, with north at the top. One more number appears on the later image when you drag the slider to the left.
Our view of Stegra steelworks, Boden (Stegra)
We believe this plant has not started making steel, because we have not seen any heat from a furnace. We expect it to start later than the company first planned, and to need more funding before then.
Why we say this
The site grew by another 46 hectares in the past year, so building work is still going on. In September 2026 the company said costs were higher than it had expected.
If building continues at the pace of the last 12 months, we expect the built area to reach about 352 hectares by September 2027. It is 306 hectares today.
Over the last 12 months we measured growth of about 3.8 hectares a month, from 260 in September 2025 to 306 in September 2026. The dotted line on the chart carries that pace forward. It is not a forecast.
Built area (typical month, May to September) (hectares)
We measured this from Sep 2021 to Sep 2026. The latest reading is 306 hectares.
measuredmeasured pace carried forwardwhat the company said- 1.Ask for the revised schedule and the cost to complete before the next drawdown. The company said in September 2026 that costs were well above its June estimate.
- 2.Ask your technical adviser to set the furnace installation dates beside our monthly heat record. The first heat from a furnace is a step you can check from outside.
- 3.Use the summer built-area figure each year as an outside check on the progress the borrower reports.
- If we see: The first heat on the siteA furnace is being tested or run, which means hot commissioning has started.
- If we see: A built area that stops growing while no heat appearsOutdoor work has either ended or paused before the plant is running. We would ask the company which of the two it is.
- If we see: A winter that is dimmer than the one beforeSome lights have been taken down. Brightness does not follow the number of people at work, so we would ask the company what changed.
What the company and the press have said, beside what we measured
Each letter matches a mark on the chart in “Test it yourself”.
- AJanuary 2026: Local press reported just over 700 employees, against an earlier target of 1,500 by early 2026, and quoted the company saying financing was affecting its schedule. (Norrlandska Socialdemokraten)Our latest reading before this was 260 hectares, in September 2025.
- BApril 2026: Trade press cited industry sources putting construction at about 60 to 70 percent complete; the company said its timeline was under review. (Eurometal)Our latest reading before this was 260 hectares, in September 2025.
- CJune 2026: Financing round closed, led by a Wallenberg Investments consortium; the company said the project timeline was under review. (Stegra press release (PR Newswire))Our latest reading before this was 260 hectares, in September 2025.
- DSeptember 2026: A review under the new owners found completion costs significantly higher than assumed in June and said more capital was needed; a new chief executive was named. (Stegra press release (Cision))We measured 306 hectares in September 2026.
- EOctober 2026: The company reported that installation of the two electric arc furnaces had begun a few weeks earlier. (Stegra)We measured 306 hectares in September 2026.
Steps that we can see from orbit before they are reported
- SeenThe built area keeps growingThe built area was 306 hectares in summer 2026. It was 260 hectares in 2025 and 133 in 2024. We first saw this in September 2026.
- SeenThe site is brighter at night than the town beside itIn the months we could measure in 2026 the site was 1.31 times as bright as Boden town. In the same months of 2025 it was 0.80 times as bright. We first saw this in September 2026.
- Not yet seenThe built area stops growingThe built area grew by 46 hectares between 2025 and 2026. When it levels off, the outdoor building work is largely done.
- Not yet seenA furnace gives off heat for the first timeWe saw no sign of heat in any of the 12 months from November 2025 to October 2026.
Brightness at night (brightness reading)
We measured this from Jan 2021 to Sep 2026. The latest reading is 32.5 brightness reading. A break in the line is a period in which we have no reading.
measuredBrightness at night of Boden town, for comparison (brightness reading)
We measured this from Jan 2021 to Sep 2026. The latest reading is 24.8 brightness reading. A break in the line is a period in which we have no reading.
measuredSigns of heat in each month (detections)
We measured this from Nov 2025 to Oct 2026. The latest reading is 0 detections.
measuredWe measured these sites up to October 2026. Every figure is one of our measurements or a linked public record. A dotted line carries the measured pace forward. It is not a forecast.
Check your own site →